(Optional)Remote Output Control

This function is available only in Japan.
The inverter remotely connects to the power company's server to obtain dispatch information. Based on the correspondence between time and output value in the dispatch information, it controls the "Maximum Active Power" output of the inverter.
1
Remote Output Control
Click and set to
,to enable remote output control.
2
Output Control Region
Power company region.
3
Output Control Duration
Output control time; the time for active power to change from 0% to 100%, or from 100% to 0%.
4
Remote Output Control Station ID
Station ID assigned by the power company.
5
Remote Output Control Server
Domain name of the power company's server.
6
PV Panel Capacity
Capacity of the PV panels connected to the power station.
7
PCS Capacity
AC capacity of the power station limited for feeding into the grid.
8
Enable Surplus Energy Purchase
When clicked and set to
, the inverter's power is controlled according to the remote output control dispatch command issued by the power company. The total output power of the station must not exceed the active power dispatch value issued by the power company.When clicked and set to
, if the load power is less than or equal to the remote output control dispatch command, the station's output power is controlled according to the dispatch command. The grid connection point can buy or sell electricity. If the load power exceeds the remote output control dispatch command, the station automatically adjusts the inverter's output power to achieve zero power at the grid connection point, meaning the grid connection point cannot sell electricity.
9
Use Certificate
Whether to verify the server's certificate when communicating with the power company's server.
10
Configure Certificate
Import the relevant certificates for encrypted communication with the power company's server into the power station.
11
Update Configuration
Update the remote output control related configuration parameters of the power station.
12
Start Connection
Initiate one communication session with the power company's server. When configuration parameters, certificates, and other conditions are met, the station will automatically perform scheduled communication with the power company's server; manual initiation is not required.
Last updated